My Grid Connected 10Kw Bergey Excel Installation

 

Page 2

Page 3

Page 4

Page 5

Page 6

Maine Guide Wind Power, LLC “Your guide to energy independence”

     The photo to the left is a view of the tower site clearing just before we dug the holes for the concrete.  The process of clearing this area took approximately 3 weeks.  Doing the work myself saved a considerable amount of money. 
     After digging the anchor holes, rebar cages were constructed and installed in the 3 anchor holes.  A rough concrete form will need to be made to help contain the concrete to a reasonable size.  In better soil a smaller hole can be constructed, thus eliminating the need for a concrete form.

     Once the concrete forms are constructed around the rebar frames, the 10 foot long anchor rods provided with the Bergey 10kw tower kit are installed within the rebar cage.  The orientation of the anchor rod needs to be at a 45 degree angle with the eye of the rod in a perpendicular orientation.  This orientation is critical, and needs to be maintained while the concrete sets up for proper guy wire orientation.

  -Rick Theriault

 