My Grid Connected 10Kw Bergey Excel Installation

 

Page 2

Page 3

Page 4

Page 5

Page 6

 

 

Maine Guide Wind Power, LLC “Your guide to energy independence”

    Two days after pouring the concrete I was able to remove the forms from around the anchors and the center tower pad.  The picture to the right shows one of the three anchor forms after the concrete hardened.
The photo to the right shows the 32"x32" tower pad.  Both the anchors and tower pad will next be back filled and the soil compacted around the concrete.  I also plan to spread a bit of gravel over the general tower site to level it a bit.

Here is the tower pad after the hole was back filled with gravel.  Now we are just waiting for the ground to settle for a couple of months as well as the concrete to cure.

  -Rick Theriault

 